Customer: Progress Energy
Location: Hamlet, NC
EPC Contractor: Gemma Power Systems, LLC
Design Engineer: General Electric Company and Black & Veatch
Phase I of the Richmond County power project is a 712 MW simple cycle power plant consisting of four General Electric 7FA units.
Gemma’s scope of work included all site construction and commissioning. Construction began in July 2000 and substantial completion was achieved in April 2001.