Customer: Connecticut Municipal Electric Energy Cooperative (CMEEC)
Location: Wallingford, CT
EPC Contractor: Gemma Power Systems, LLC
Design Engineer: Careba Power Engineers, LLC
The A.L. Pierce Repowering Project consists of one simple cycle General Electric 7EA combustion turbine relocated to an existing building after four years of storage.
Gemma’s scope of work included complete plant design, site demolition, site development, equipment installation, enhancements to the existing building, electrical interconnection, start-up and commissioning. Demolition began in late October 2006 and substantial completion was achieved in October 2007.