Customer: Panda Power Funds
Location: Lycoming County, PA
EPC Contractor: Gemma – Lane Patriot Partners
(a joint venture with The Lane Construction Corp.)
Design Engineer: POWER Engineers
The Panda Patriot Power Project is an 800 MW natural gas-fired combined cycle generating facility consisting of two 400 MW single-shaft power trains. The plant uses Siemens SGT6-8000H gas turbines, Siemens SST-5000 steam turbines, Siemens SGEN6-H hydrogen-cooled generators, Vogt “Smart-Box” heat recovery steam generators and air cooled condensers. Gemma also constructed ancillary systems and buildings as well as the electrical interconnection facilities and tie-ins for natural gas, water and wastewater.
Limited notice to proceed was received on July 16, 2013. Full notice to proceed was received on Dec. 19, 2013. Substantial completion was achieved in June 2016.